Services: Tender Project for 35 metro stations - Design of internal structures, auxiliary structures and earth retaining structures
Summary: Structures basic design for 35 new metro stations, divided into 9 types. 27 passenger stations will be on line 2 (length 27 km) and 8 stations will be built on the branch Av Faucett - Av Gambetta (7.6 km long)
Constructive methods considered in the study included Vertical NATM excavation (vertical tangent shafts) and Cut-and-cover. The design and modelling were developed based on detailed seismic studies of soil-structure interaction using seismograms of large earthquakes in Chile and Peru.
GLOBAL PROJECT OF THE LINE 2 AND AV. FAUCETT - AV GAMBETTA
Contacts
NSE • Consultores de Engenharia, Lda
Avenida da República, n.º 41, 1º Dto., 1050-187 Lisboa
Telephone: +351 217 942 533
Fax: +351 217 942 535
E-mail: geral@nse.pt
NSE · Consultores de Engenharia Lda. 2017 ©