Back

Bridges and Viaducts

RIBEIRA DE JORJAIS BRIDGE

Transmontana Highway (PPP) - A4/IP4 – Vila Real (Parada de Cunhos) / Quintanilha

Client
CAET XXI (Construction Consortium for the Transmontana PPP) / Senerpor, S.A.
Location
Transmontana Highway (PPP) - A4/IP4 – Vila Real (Parada de Cunhos) / Quintanilha
Design date
2009 - 2010
Construction date
2011 - 2012
Services
Preliminary Study; Detailed Design; Technical Assistance to the Construction
Construction
FCC – Construcción, S.A. (Portugal) / Soares da Costa, S.A.
Summary

Dual deck with haunched prestressed concrete box girders. Construction by the Balanced Cantilever Method.

Length / Span / Height / Width

365 m / 110 m / 56 m / 2x12.8 m